HS2 finishes two-mile-long Bucks railway cutting in record year for earthworks

  • Download new images showing progress on the 2.1-mile-long Calvert cutting and the five bridges crossing it near the Buckinghamshire villages of Calvert Green and Twyford. Download photos of earthworks elsewhere on the project.
  • The completion of the excavation come as EKFB - HS2’s contractor in the area - celebrates a record year for earthworks delivery with 18 million cubic metres shifted this year, putting them more than 40% ahead of target for the year.

Construction workers on the HS2 project have finished digging their second-longest cutting at the end of a record year for earthworks between London and Birmingham.

The 2.1 mile-long (3.4km) Calvert cutting will hide high-speed trains as they pass the Buckinghamshire villages of Calvert Green and Steeple Claydon, roughly following the route of the former Great Central Railway, which closed in the 1960s.

While the old railway was on an embankment, the new one has been pushed down in the landscape and will be crossed by five major road and rail bridges.

Work began on the cutting in 2022, led by HS2’s main works contractor in the area, EKFB – a team made up of Eiffage, Kier, Ferrovial Construction and BAM Nuttall.

They worked with specialist earthmovers Kier Transportation Ltd. to shift more than 1.6 million cubic metres of material to create a level surface for track to be laid on. The equivalent of 274 Olympic-sized swimming pools.

This material – largely a mix of earth and clay – is being reused elsewhere on the project to create embankments, noise barriers and landscaping to blend the railway into the surrounding countryside.

With the 2026 earthworks season now largely complete, EKFB has shifted an incredible 65 cubic metres of material across all their sites between the Chilterns and South Warwickshire to date – and look set to end the year more than 40% ahead of target.

They are one of two major contractors that have renegotiated their contracts as part of HS2 CEO Mark Wild’s reset of the high-speed rail project, which is designed to control costs and improve productivity.

Aerial view of the Calvert cutting looking south as it passes the site of the future Infrastructure Maintenance Depot Nov 2026

HS2 Ltd Project Director Bill Clowes said:

“It’s great to see how much progress has been made at Calvert and our other major cuttings this year. Boosted by the unusually dry summer, we were able to shift an incredible amount of material and for the first time, you can really get a sense of what the railway will look like once complete.

“I’d like to thank everyone involved in this enormous effort. This year’s record numbers would not have been possible without the huge amount of planning and preparation they’ve put in over the last few years, so that when we had the dry weather, we could really hit the ground running and make the most of every hour of the working day.”

The cutting – which is up to 2.5 metres below ground level – starts south of the village of Calvert Green and ends near Twyford. It is crossed by four major roads and the East-West railway, as well as three drainage culverts and 12 major utility diversions.

This made the dig a major logistical challenge, with the bridges having to be built before the excavation could be completed. The last bridge – which carries West Street across the cutting – was opened earlier this month.

Unlike most other cuttings on the project, which are only wide enough for two tracks, the southern half of the Calvert cutting is 56 metres wide, to allow two conventional railway lines to run alongside the high-speed lines. This is to allow Network Rail space to reinstate the old freight line between Aylesbury and FCC waste facility at Calvert to link in with East-West Rail in the future. 

With the bulk excavation now complete, the team are turning their attention to the drainage, before a final surface layer of aggregate is added to create a stable foundation for the track.

Aerial view from West Street bridge looking north along the Calvert cutting Nov 2026
View looking north along the Calvert cutting from under West Street bridge Nov 2026

EKFB Project Manager Gavin Llewellyn said:

“Construction in and around Calvert has made significant progress this year, and the opening of the West Street overbridge is another key milestone. We recognise that our work has caused disruption for people living nearby, which is why we're focused on reopening roads across Buckinghamshire as quickly as possible. So far, we've reopened fourteen roads across the county, to keep communities connected as work on the railway continues.

"Completing the earthworks at Calvert Cutting is a major achievement and an important step towards the next phase of construction. Over the winter, our teams will focus on preparing the track bed for the railway, building on the progress made this year. I'd like to thank everyone involved for their hard work and commitment in reaching this milestone."

Across their whole 80km of the project, EKFB have more than a thousand items of plant equipment on site, including hundreds of huge articulated dumper trucks and excavators. Some of these works are self-delivered by EKFB and others are delivered by specialist earthworks subcontractors such as Kier Transportation, Blackwells, Plantforce, Flannery and Walters.

Excavator at work on the Barton Mixbury cutting Spring 2023

This year they shifted a combined total of 18 million cubic metres of material, bringing their total since the start of construction to 68 million cubic metres.

This leaves around 18 million cubic metres still to be moved in EKFB’s area before the track can start being laid in 2030.

Recognising the need for a new generation of skilled drainage operatives across their whole 80km stretch of the project, earlier this year EKFB teamed up with the Bicester Skills Centre to create 170 bespoke training places for people in the area.

They will help EKFB deliver around 200km of drainage, including trackside ditches and culverts and balancing ponds and leave a legacy of transferrable skills for the trainees.

The longest cutting on the HS2 project is the 2.4-mile-long Barton-Mixbury cutting which straddles Oxfordshire and Buckinghamshire. Other major cuttings, at Turweston in Northamptonshire, Waddesdon in Bucks, and Ladbroke, in South Warwickshire, are also approaching completion, with all civil engineering on the project expected to be finished by 2029.