HS2 rail freight to cut 10,000 lorries from Euston roads: Rail Minister and Leader of Camden Council waving off freight train at Euston
HS2 rail freight to cut 10,000 lorries from Euston roads: Rail Minister and Leader of Camden Council waving off freight train at Euston

HS2 rail freight to cut 10,000 lorries from Euston roads

  • Rail freight will remove up to 170,000 tonnes of excavated material from the Euston site
  • Rail Minister and new Leader of Camden Council see off freight train, the Green Progressor, at Euston
  • Government, HS2 and the rail industry are working together to reduce the impact of construction on communities around Euston
  • View and embed video of Euston here: HS2 Materials By Rail London Euston 

On Monday (16 November), Rail Minister Lord Hendy visited HS2’s Euston site to see how rail freight is being used to remove excavated material as the team prepares the ground for the new HS2 station.

HS2’s station construction partner, the Mace Dragados joint venture (MDJV), has begun the bulk excavation of the station site. This involves excavating to a depth of around seven metres, where the new HS2 platforms will be built.

In total, up to 170,000 tonnes of excavated material is expected to be removed from the site by rail. HS2’s team is using a new loading facility beside the disused Track 17 at Euston station.

From there, the material is being transported to Forders Sidings in Bedfordshire for reuse at the Stewartby Brickworks development.

Working closely with Network Rail and the wider rail industry, the programme has been carefully planned to enable freight trains to operate alongside passenger services at Euston.

The programme will remove the need for more than 10,000 heavy goods vehicles (HGV) on roads around Euston and across London.

Rail Minister, Lord Hendy said:

"Moving this soil by rail will mean thousands fewer HGV journeys through the streets around Euston, helping to reduce disruption for local people, improve road safety and cut carbon emissions.  

"This is part of the real progress we are making on HS2. All 23 miles of the tunnels between Old Oak Common and Birmingham have now been dug and more than 80% of the project’s major structures are under construction or complete. Under new leadership, HS2 Ltd is delivering more for every pound having moved 20 million cubic metres of earth - 16% ahead of plan.” 

Around 35,000 tonnes of excavated material was transported during successful trials between February and September 2026. The trials showed that each train could carry more material than originally anticipated and that they could be reliably operated alongside with passenger services.

A further 135,000 tonnes is expected to be removed during the next phase over the coming ten months.

Up to two trains a day, operated by GB Railfreight, will be used during the main excavation programme, with each train able to carry approximately 715 tonnes of material, equivalent to around 45 HGVs.

Andy Swift, Stations Delivery Director, HS2 said:

“We are committed to reducing the impact of our work on the communities around Euston. Moving material by rail is one of the most effective ways we can reduce the number of construction vehicles using local roads.

“Delivering this programme has required careful planning with Network Rail, GB Railfreight and our construction partners. That collaboration will allow us to move up to 170,000 tonnes of material by rail while passenger services continue to operate at Euston.”

Cllr James Slater, Leader of Camden Council, said:

“For many years, Camden has called for construction materials to be removed from Euston by rail, so it is excellent to see this now being delivered at scale. Taking more than 10,000 lorries off Camden's roads is a significant achievement that will reduce disruption for our residents and businesses, improve air quality and help cut carbon emissions.

“This is exactly the kind of practical measure that will make a real difference to our communities living alongside the Euston site and on routes in and out of our borough. As construction progresses, we want to see every opportunity taken to further increase the amount of material moved by rail, and we will continue supporting HS2 and partners to explore all options to maximise the benefits that this measure can deliver for our residents.”

Moving the material by rail also helps reduce the HS2’s carbon impact, as rail freight produces up to 76 per cent fewer CO₂ emissions than road freight when transporting the same weight of material over the same distance.

The Euston rail freight programme is part of HS2’s wider commitment to make better use of the existing railway during construction. Freight trains have brought aggregate into sites in Buckinghamshire and Birmingham, delivered tunnel segments to West Ruislip and Willesden, and carried millions of tonnes of excavated material away from construction sites around Old Oak Common.

By bringing this approach to Euston, the government, HS2 and the rail industry are working together to reduce local lorry traffic and its impact on local communities.

Patrick Cawley, Director for On Network Works at Network Rail and HS2, said:

“We’re proud to be working with HS2 and our rail industry partners to help make this programme possible. It’s been a real collaborative effort across many different teams to safely accommodate these freight trains alongside the day-to-day operation of one of Britain’s busiest stations, while keeping passengers moving.

“It’s also a great example of what the railway can do best. Moving more materials by rail means fewer lorries on local roads and lower carbon emissions, and we’re pleased that the existing railway is playing such an important role in supporting the delivery of HS2 at Euston.”

Each train will comprise two locomotives and up to 12 wagons. This configuration will maximise the amount of material carried while allowing sufficient time for loading and unloading.

Track 17 is expected to remain available until early 2029. HS2 Ltd will continue working with the Euston Delivery Company and other partners to explore opportunities to use the facility to support construction across the wider Euston campus.